12.20.02 - The launch of NASA's ICESat and CHIPSat spacecraft aboard a Boeing Delta II Expendable Launch Vehicle has been postponed.
12.11.02 - The two-day operation to install the two halves of the payload fairing around the payload atop the rocket begins today and is the final major activity to be performed before launch.
12.05.02 - NASA's TDRS-J Tracking and Data Relay Satellite was successfully launched from Cape Canaveral at 9:42 p.m. aboard a Lockheed Martin Atlas IIA rocket.
11.27.02 - In the Spacecraft Assembly and Encapsulation Facility-2 (SAEF-2) the TDRS-J spacecraft was mated to the payload adapter on Nov. 20 and encapsulated into the payload fairing on Nov. 21.
11.20.02 - The TRDS-J spacecraft is undergoing final checkout at the Spacecraft Assembly Encapsulation Facility-2 in the KSC Industrial Area.
11.14.02 - The TDRS-J spacecraft is undergoing final checkout at the Spacecraft Assembly and Encapsulation Facility-2 in the KSC Industrial Area.
11.07.02 - The TDRS-J spacecraft is at the Spacecraft Assembly and Encapsulation Facility-2 in the KSC Industrial Area.
10.30.02 - The TDRS-J spacecraft is at the Spacecraft Assembly and Encapsulation Facility-2 in the KSC Industrial Area undergoing electrical testing.
10.24.02 - The TDRS-J spacecraft arrived at the Kennedy Space Center at 6:10 a.m. last Thursday, Oct. 17, and was taken to the Spacecraft Assembly and Encapsulation Facility -2 in the KSC Industrial Area.
10.16.02 - The TDRS-J spacecraft has completed testing at the Boeing Satellite Systems plant in El Segundo, Calif., and is scheduled to arrive at Kennedy Space Center's Shuttle Landing Facility tomorrow, Oct. 17, aboard a C-17 aircraft.
10.09.02 - The Atlas II launch vehicle is at the Lockheed Martin factory in Denver, Colorado undergoing final assembly, integration and testing.
10.02.02 - The Atlas II launch vehicle is at the Lockheed Martin factory in Denver, Colorado undergoing final assembly, integration and testing.
09.25.02 - The Atlas II launch vehicle is at the Lockheed Martin factory in Denver, Colorado undergoing final assembly, integration and testing.
09.18.02 - The Atlas II launch vehicle is at the Lockheed Martin factory in Denver, Colorado undergoing final assembly, integration and testing.
09.04.02 - The Atlas II launch vehicle is at the Lockheed Martin factory in Denver, Colorado undergoing final assembly, integration and testing.
08.28.02 - The Atlas II launch vehicle is at the Lockheed Martin factory in Denver, Colorado, undergoing final assembly, integration and testing.
08.21.02 - The Atlas II launch vehicle is at the Lockheed Martin factory in Denver, Colorado undergoing final assembly, integration and testing.
08.14.02 - NASA and Lockheed Martin have agreed on a new launch date of Nov. 20.
08.07.02 - The Atlas II launch vehicle is at the Lockheed Martin factory in Denver, Colorado undergoing final assembly.
07.31.02 - The GALEX spacecraft is at the Orbital Space Systems Group facility in Dulles, Virginia, and is expected to arrive at KSC to begin final processing no earlier than August 26.
07.24.02 - The GALEX spacecraft is at the Orbital Space Systems Group facility in Dulles, Virginia and is expected to arrive at KSC to begin final processing on or about August 26.
07.17.02 - The GALEX spacecraft is at the Orbital Space Systems Group facility in Dulles, Virginia, and is expected to be shipped to KSC for final processing in mid-August.
07.10.02 - The GALEX spacecraft is at the Orbital Space Systems Group facility in Dulles, Va., and is expected to be shipped to KSC for final processing in mid-August.
07.03.02 - The launch of the Boeing Delta II rocket with NASA's CONTOUR spacecraft occurred at 2:47:41.366 EDT from Pad 17-A at Cape Canaveral.
06.27.02 - The launch of the NOAA-M Polar Orbiter from NASA's Space Launch Complex 4 West occurred successfully on Tuesday, June 24.
06.19.02 - The Titan II/G-14 prelaunch preparations continue to progress on schedule.
06.12.02 - The Titan II/G-14 prelaunch preparations continue to progress on schedule.
06.05.02 - At SLC-4W, the Titan II/G-14 prelaunch preparations continue to progress smoothly.
05.22.02 - At SLC-4W, the Titan II/G-14 prelaunch preparations continue to progress smoothly.
05.15.02 - At SLC-4W, the Titan II/G-14 prelaunch preparations continue to progress on schedule.
05.09.02 - The launch of Aqua EOS - PM from NASA's Space Launch Complex 2 West occurred successfully on Saturday, May 4.
05.01.02 - Preparations are on schedule for the launch of Delta/Aqua on Saturday, May 4 at 2:55 a.m. PDT.
04.24.02 - On April 18, the Aqua spacecraft was mated atop the Boeing Delta II launch vehicle at NASA's Space Launch Complex 2 located on North Vandenberg Base.
04.17.02 - This week, launch and spacecraft managers scheduled the launch of Delta/Aqua on the Western Range for Thursday, May 2 at 2:55 a.m. PDT.
04.10.02 - The Aqua spacecraft remains at the Spaceport Systems International (SSI) payload processing facility located on South Vandenberg Air Force Base.
04.03.02 - The Aqua spacecraft is at the Spaceport Systems International (SSI) payload processing facility located on South Vandenberg Air Force Base.
03.27.02 - The Aqua spacecraft is at the Spaceport Systems International (SSI) payload processing facility located on South Vandenberg Air Force Base.
03.20.02 - The Aqua spacecraft is at the Spaceport Systems International (SSI) payload processing facility located on South Vandenberg Air Force Base.
03.13.02 - This week TDRS-I is being raised to its final orbital altitude of 22,240 miles.
03.06.02 - The Flight Readiness Review for TDRS-I was completed on Monday, March 4 and launch preparations are on schedule for a liftoff on Friday.
02.27.02 - At SAEF-2, loading of the spacecraft with propellants was completed on Feb. 20 and the spacecraft was mated to the payload adapter on Feb. 22.
02.20.02 - The NOAA-M spacecraft is at the Lockheed Martin plant in Sunnyvale, Calif.
02.13.02 - At SAEF-2, prelaunch processing of TDRS-I continues to occur on schedule.
02.06.02 - Attached to an L-1011 aircraft, NASA's High Energy Solar Spectroscopic Imager (HESSI) mounted atop an Orbital Sciences Pegasus XL rocket, departed from Cape Canaveral Air Force Station at 2:29 p.m. EST on Tuesday, Feb. 5.
01.31.02 - On January 28 at a follow-up Flight Readiness Review, NASA and Orbital Sciences cleared the Pegasus XL launch vehicle for flight.
01.23.02 - The launch of Pegasus/HESSI has been re-targeted for NET Feb. 5.
01.16.02 - At Vandenberg Air Force Base in California, the HESSI spacecraft was remated to the Pegasus launch vehicle on Dec. 20 and the payload fairing was installed around HESSI on Jan. 11.